No Guesswork. Just a Well-Built Timeline.
Because Great Homes Don’t Happen Overnight. We believe the best results come from careful planning, open communication, and doing things the right way.
Timelines
The Bella Vista team has decades of experience in building and remodeling. So naturally we’ve gained a lot of skill, knowledge and understanding over the years. Here, we share our insights in design and construction because we want you to be as comfortable with the process as you are in your new home. Every project follows a structured process designed to keep things clear, collaborative, and well-paced. While timelines can vary based on scope, approvals, and location, the outline below reflects a typical remodel or addition experience.
Phase 1: Design & Planning
Timeline: 2–3 Months
This phase is all about defining your vision and refining the details.
Explore layout options for your remodel or addition
Finalize design decisions and materials
Develop electrical plans and exterior elevation drawings
Ensure the design is fully thought through before pricing begins
Taking time here allows us to avoid costly changes later and build with confidence.
Phase 2: Pricing & Proposal
Timeline: 3–6 Weeks
Once design development drawings are approved:
We create a detailed, written scope of work specific to your project.
Plans are sent to our trusted trade partners for bidding (2–3 weeks)
A fixed-price proposal is built from real numbers—not estimates
At this time, we meet in our office to review the proposal line by line together. If changes are requested after this meeting, pricing adjustments typically add 2–3 additional weeks.
Phase 3: Contract & Permits
Timeline: 6–12+ Weeks (varies by location)
After the proposal, scope, and contract are approved and signed:
Plans return to design to prepare the permit set (≈ 2 weeks)
Permit submission to the city (≈ 4–6 weeks for approval)
Homes in conservation districts require additional approval before city permits, adding 4–8 weeks
Permit timelines are determined by the city and can vary.
Phase 5: Final Walkthrough & 30-Day Review
Final site walkthrough with your Project Manager
Project Closure Document created together
30-day Customer Service Review begins so you can live in the space and note any items
Any outstanding items are addressed promptly after review
Phase 4: Construction Begins
Timeline: 9–10 Months (for whole-home remodels or 2nd-story additions)
Once permits are approved, we schedule a kickoff meeting and begin construction.
Months 1–2
Deconstruction, foundation and dirt work
Month 3
Foundation completion and framing begins
Month 4
Framing continues
Roof and windows installed
Home is dried in
Month 5
Mechanical rough-ins: HVAC, electrical, and plumbing
Months 6–7
Insulation
Drywall installation
Flooring and tile prep
Month 8
Tile installation
Cabinetry installation
Month 9
Interior trim
Paint
Month 10
Countertops installed
Fixture and final trim-out
Final punch list and project completion
Throughout construction, required city inspections take place. These inspections are necessary and can occasionally speed up or delay progress depending on city scheduling.